Introduction of Heavy Axle Loads in Europe:
The Economics of 30 Tonne Axle Load Operations on
the Malmbanan
Allan M. Zarembski
ZETA‑TECH Associates, Inc.
Cherry Hill, NJ USA
Björn Paulsson
BANVERKET
Borlange, SWEDEN
Abstract:
While
the economics of heavy axle load operations has been established in North
America and Australia, it has not been proven to date in Europe. Under
increasing international competition, the movement of iron ore from mines in
Northern Sweden to ports in Norway and Sweden, was looking for ways to reduce
transportation costs and increase competitiveness. In order to determine if
heavy axle load operations was an answer, a two pronged study was undertaken on
the effects of increasing axle loads (from the current 25 Tonnes to a proposed
level of 30 Tonnes) and increasing train size.
A
parallel study performed by consultant ZETA-TECH Associates, Inc. of the USA
and an internal Banverket/Jernbaneverket team, examined both the effect of the
heavy axle loads on track damage (and maintenance costs) and on the overall
cost of rail operations. The results, which was supported by both team efforts,
was that while track maintenance costs would increase by approximately 13%,
overall operating costs (to include track maintenance) would be reduced by
almost 30%. Based on the results of this study, orders have been placed for a
new generation of 30 Tonne axle load wagons for use on this line.
The
economics of heavy axle loads, particularly for the transport of high volume, high
density commodities, has been well established in North America and Australia
where 30 Tonne axle loads have been the “norm” for decades. In fact, the
economics of these heavier axle loads have been so strong that recent moves
have been towards even higher axle load levels of 33 Tonnes and greater[3].
As European railways come under increasing pressure to reduce operating costs,
and to even show a profit in their freight (goods) operations, it is only
natural that they look at the costs and benefits associated with heavier axle
loads and see if the benefits experienced elsewhere can also be realized in the
European environment.
This
was clearly the case recently, in northern Sweden and Norway, for the large
scale movement of iron ore from the LKAB mines in Kiruna and Gällivare, to the ports of Narvik, Norway and Luleå, Sweden. As international competition increased,
the mine owners looked at alternate ways to reduce their costs, with one such
way being reducing transportation costs by using heavier wagons and longer,
heavier trains. Since this movement had relied on 25 Tonne axle load wagons,
the lowest axle load of all the major international iron ore movements, it was
logical to look at increasing the axle load to 33 tonnes. However, the impact
of this increased axle load had to be carefully examined in light of the
current track conditions on the Swedish and Norwegian line segments over which
this movement took place.
In
order to assess the impact of increasing axle loads (and train length), a
parallel research approach was adopted. The first part of the study was
performed by ZETA-TECH Associates, Inc., a Cherry Hill, New Jersey, USA firm
with strong experience in the evaluation of heavy axle load operations and
impact in North America and elsewhere. ZETA-TECH used its previously developed
heavy axle load methodology to assess the impact of the increased axle loads on
track damage, and corresponding levels of track maintenance. It further
evaluated the overall economics of the heavier wagon, heavier train options,
again using North American based analysis methodology.
The
second part of the study was performed by a joint
BANVERKET/SJ-Jernbaneverket/NSB-LKAB team that independently examined all of
the major track and operating issues associated with the increased axle load
operations. These multidiscipline teams used internal studies, external
research (to included external university and consultant research), and foreign
experience to examine and quantify these effects, independent of the ZETA-TECH
team. Here too, the focus was on both the assessment of increased track and
structure damage (and maintenance costs) and the impact on overall operating
costs.
By
allowing these two teams to work independently and in parallel, and by
comparing the two sets of results at the end of the studies, a mechanism was
set up to provide the information needed to determine if heavier axle loads was
right for Europe (and for the Malmbanan operation in particular).
The
analysis performed by ZETA-TECH Associates, Inc. consisted of two major
efforts:
·
An assessment of
the increased track and structure damage that would be caused by the operation
of heavier wagons
·
An assessment of
the overall operating costs associated with the heavier wagons and heavier
trains.
The
effect of increasing axle loads was from the current 25 tonnes to an increased
level of 30 tonnes. In addition the effect of introducing new equipment, with radial trucks, and improved net to
tare ratios, was incorporated in the analysis as was the effect of increasing
operating speed from the existing 50 km/hr to 60 km/hr.
Track
and Structures costs considered in the analysis included:
·
Rail
·
Sleepers (both wood
and concrete)
·
Track geometry (to
include the effects of ballast and subgrade)
·
Turnouts
·
Bridges
The
analysis addressed both capital costs (for major track and bridge replacement
work) and maintenance costs (the day-to-day cost of keeping the railway in safe
operating condition). In addition to track costs, the expected increase in
maintenance/replacement cost for all bridges (steel, concrete, and stone) was
quantified.
The
approach used was based on a methodology previously developed by ZETA-TECH
Associates Inc. and used in a series of heavy axle load studies on North
American railroads. This methodology is based on track component behavior
observed on several North American railways, which indicates that, on a
per-axle basis, track cost increases can be non-linear with increases in axle
loads. In the analysis of the track and its key components, this heavy axle
load effect was addressed through the development of a set of damage factors,
with separate damage exponents and damage factors calculated for each track
component and component failure mechanism.
For
the assessment of overall operating costs, only the direct costs of movement
was considered. In general, the direct costs of movement are those which vary
with the movement of trains and cars; administrative and overhead expenses, and
those costs (such as snow removal) that logically do not vary with train size,
axle load, or traffic volume, were excluded.
Thus,
direct costs of movement considered in the analysis included:
·
crew wages
·
electric power cost
·
equipment
maintenance expense (cost of maintenance, plus cost of shop operation and
direct supervision)
·
equipment ownership
expense (purchase price amortized over the economic life of the locomotives and
freight wagons
·
track maintenance
expense
·
an annualized cost
of required bridge upgrading or replacement to carry the heavier loads (effect
of a reduction in bridge life)
As mentioned previously, the study involves the comparison of two different types of wagons at two axle loads. Table 1 shows the characteristics of the 4-axle wagons. Note that the 100 tonne wagon achieves a substantial improvement in net-to-tare over the 80-tonne wagon, carrying 25% more net load with the same tare weight.
Table
1: Characteristics of Freight Wagons
|
|
Base
Wagon |
High
Capacity Wagon |
|
Length |
8,400 mm |
10,300 mm |
|
Tare Weight |
20 tonne |
20 tonne* |
|
Net Capacity |
80 tonne |
100 tonne* |
|
Gross Weight |
100 tonne |
120 tonne |
|
Cost (SEK) |
600,000 |
750,000 |
*The new wagon actually have a tare weight of
< 20 tonnes and a capacity > 100 tonnes
The analysis also involved the determination of the benefits of increased train weight. By looking at different combinations of axle load and train weight, it was possible to isolate particular benefits of heavier axle from the more general benefits of increased train weight. Table 2 shows three scenarios for which costs were developed in this analysis.
Table
2: Operating Scenarios Analyzed
|
|
Base
Case |
Heavy
Axle Load Case |
Longer
Train Case |
|
Cars per Train |
52 |
68 |
85 |
|
Net Wt. |
4,160 |
6,800 |
6,800 |
|
Tons Ore/Yr. |
22,900,000 |
22,900,000 |
22,900,000 |
|
Cycle Time (Load to Load) |
|
|
|
|
Axle Load |
25 tonnes |
30 tonnes |
25 tonnes |
Taking all these factors into account, ZETA-TECH quantified the expected increase in track and equipment maintenance costs associated with an increase in maximum car weights, as well as the savings available to LKAB from the operation of heavier trains. Note; the current equipment was more than 30 years old, and decisions were being made regarding what type of replacement equipment should be purchased. In addition, the route from Kiruna to Narvik was nearly at the maximum capacity permitted by current operating practices, and investment of some kind (in track, wagons, locomotives, or in all these areas) were required in order to accommodate a planned expansion of iron ore production.
A
parallel analysis was conducted by a set of Banverket-Jernbaneverket-LKAB
teams, broken up into individual technical areas. Each team addressed a key
infrastructure, equipment, or operating issue from both the technical and
economic perspective. The analysis teams were divided up into Swedish and
Norwegian organizations, with Bjorn Paulsson of Banverket serving as Project
Leader for the Swedish organization and Oyvind Brustad of Jernbaneverket
serving as Project Leader for the Norwegian organization. Overall program
direction was under the supervision of a steering group composed of:
Nils-Erik Bergstrom Banverket
Borlange
Bjorn Paulsson Banverket
Borlange
Ivar Hagland Jernbaneverket Oslo
Oyvind Brustad Jernbaneverket
Trondheim
Birger Norberg LKAB
Kiruna
Ake Bostrom MTAB Kiruna
Thomas Nordmark MTAB
Kiruna
The
results of the two sets of studies was a comprehensive set of 33 reports,
dealing with all aspects of the heavy axle load question. What was of particular
note was that the two conclusions were the same, that increasing axle loads to
30 Tonnes made economic sense for this line.
The
results of both studies showed that while measurable increases in track
maintenance costs will occur under the operation of heavier axle load wagons,
these costs will be more than offset by reductions in operating costs. Thus, on
the BANVERKET trackage, the expected
increase in track maintenance costs was of the order of 13% with heavier axle
loads. If grinding and lubrication are carried out to North American standards,
this increase would drop significantly.
However, as noted above, this increased track and structure maintenance costs are more than offset by the other operating costs with the result that there is a significant economic benefit to increasing axle loads on the Malmbanan and Ofotbanen beyond the current 25 tone maximum.
Specifically,
the analyses showed that:
·
Operation of
68-wagon trains with 100 tonne load
capacity (30 Tonne axle load) produced a reduction of approximately 30% in
direct operating costs over the base case (52 wagons of 80 tonne capacity), on
both routes, taking into account the expected increase in track maintenance
costs as a consequence of the increase in axle loads.
·
Assuming a “worst case” increase in track costs,
savings remained in the range of 27%.
·
The increase to 30
tonne axle loads reduces costs by about 50% more than simply increasing train
length, without increasing axle loads.
·
The increase in
axle loads also reduces the number of trains that must be operated to carry the
current and future volumes of iron ore, freeing up line capacity for other
traffic and allowing the more efficient scheduling of maintenance work.
Table
3 presents a summary of the analysis results.
Based on the results of this study, the decision was made to purchase new heavier axle load equipment, with 100 Tonne capacity (30 Tonne axle load) and radial bogies. Prototype orders have already been placed, with 68 trainsets of 68 wagons each, to be ordered upon completion of acceptance tests.
Table 3: Estimate of Costs and Savings
Operation of 100-Tonne Wagons on the Kiruna to Narvik Line
Cost per Year (All Costs in Million SEK)
|
Cost Category |
Base Case |
HAL Case |
Longer Train Case |
|
Locomotives |
|
|
|
|
Ownership |
46.780 |
34.666 |
34.666 |
|
Maintenance |
33.080 |
12.141 |
12.141 |
|
Cars |
|
|
|
|
Ownership |
26.051 |
22.964 |
26.051 |
|
Maintenance |
32.199 |
13.462 |
35.040 |
|
Track Cost |
35.010 |
37.860 |
35.010 |
|
Electric Power Cost |
10.145 |
8.681 |
11.272 |
|
Crew Cost |
29.430 |
18.004 |
18.004 |
|
Total |
212.696 |
147.779 |
172.184 |
Notes: In each case, annual volume of
ore is 15.9 M tonnes to Narvik,